Can Teamcity queue builds for later in the day?

I have a Teamcity project that is watching a git repo for PRs. When a PR is opened/changed/etc a build goes. This is working fine.

What I am wanting is for Teamcity to recognize there is a PR that needs to be built, but for it to hold on to that build until a specified time of day (I want to run mine at night, say 1AM). This could happen multiple times (there could be many PRs in waiting to be built @1AM.

Is this possible? If so, what settings would I manipulate? I have looked all around the Build Configuration, but could not find the proper settings to do what I desire.

Thanks ahead of time for any help!

1
2 comments

Can you not just use a scheduled trigger? You can set it to only build if there are any changes.

0
Avatar
Permanently deleted user

Luke,

Thanks for the tip, this worked perfectly. 

I did have to also tell it which VCS branches to watch (I assumed it would watch all by default, it did not).

 

0

Please sign in to leave a comment.